Monday 22 November 2010

It is all systems go!

On the 14th October our DA was approved by Baulkam Hills Council, taking less than 4 weeks, which was a delightful surprise to us. Last week Right Build began work on our block after the construction certificate was issued.
 A bit of digging and clearing.

 The essential port-a-loo.
The slab should be poured late this week, or early next week.

Wednesday 3 November 2010

Colours Colours Everywhere

Over the past week or so we have been picking internal colours. I must say that this is my least favourite part of the building process. But, despite my trepidation we got through it and are very happy with our choices.
All our tiles were upgrades and we are yet to see the final bill, so hopefully it is not too much of an ouch!

Kids bathroom: Grey floors, white walls and the mosaic feature tile around the bath, shower recess and around the top of the vanity. White vanity with snow c/s top.

Ensuite, powder and laundry colours. No feature tile. vanity in blackened linewood, snow c/s benchtop.
                                       

Kitchen. White laminate cupboards (matte finish), c/s snow benchtop, burnished wood for bottom of the island, and spring glass splashback.